Green Mountain Power Dam and Spillway Improvements
Specialty dam and spillway improvements across Vermont.
- Location
- Multiple Sites, VT
- Delivery Method
- CM at-Risk, Design-Bid-Build
- Market
- Manufacturing / Industrial
- Client
- Green Mountain Power
- Region
- Northeast
Project Overview
PC’s work for Green Mountain Power includes specialty dam and spillway improvements to address deterioration issues at six distinct sites across Vermont. Work included refacing existing deteriorated concrete dam, replacing concrete crest to enable the installation of an Obermeyer inflatable crest gate system, and refacing existing concrete base slab and walls for the primary spillway.
PC self-performed concrete demolition, dam installation, piping, rigging, equipment start-up, spillway face access construction, and cast-in-place concrete structures.
THE PC / GMP HISTORY
PC’s four-decade collaboration with Green Mountain Power began with the construction of the Bolton Falls Hydroelectric Plant in 1985. Today, our Special Projects Group continues to provide key construction services on over 200 contracts in Vermont, New Hampshire and New York.
6,000
Square Feet Dam Facing Repaired in Essex
250
Foot-Long Obermeyer Gate System Installed
Our Clients
GMP has very specialized needs and complex infrastructure at our many sites across Vermont, New Hampshire and New York. PC has been instrumental in our ability to keep up with the ever-changing needs of our industry over the past two decades, delivering exceptional service and top-notch quality construction every step of the way.