From Plattsburgh to the Palmetto State

| By

Schluter Systems Manufacturing Facility, Spartanburg, SCSchluter Systems Manufacturing Facility, Spartanburg, SC Even after years of hard work, dedication, and planning, the stars don’t always align. But, sometimes, those unexpected turns lead to even bigger opportunities.

For the past two and a half years, PC Construction has worked alongside Schluter Systems to plan the construction of a new manufacturing facility in Plattsburgh, New York. The project has been a tremendous undertaking and required commitment, teamwork, and endless coordination. While the team put their hearts into bringing this project to life in New York, the plan ultimately shifted, and the project found a new home in Duncan, South Carolina.

Although the change of location meant a different path forward, it also opened the door to an exciting opportunity for PC Construction. This project for Schluter Systems represents our largest manufacturing facility project in the Southeast.

The new 500,000-square-foot manufacturing facility will occupy a 10-acre footprint on a 70-acre site, with space for manufacturing operations, offices, and automated racking. This new space will allow Schluter to increase its manufacturing capacity and improve efficiency.

We are fully mobilized and excited about our progress to date, including the completion of site preparation. This extensive effort involved hauling in 350,000 cubic yards of fill to bring the site to grade – the equivalent of 90 Olympic-size swimming pools!

In the coming months, we’ll place 25,000 cubic yards of concrete, including 15,000 in foundations and 10,000 in tilt wall panels, some of which will be 75 feet tall. Crews will set 1,600 tons of steel to form the structure of the building. More than 23,000 square feet of glazing will complete the building’s shell to bring the exterior to life. Then 44,000 linear feet of piping will connect 51 rooftop energy recovery units and the rest of the mechanical system.

Those numbers are big, but the people behind them are what make this project work. Our team picked up years of planning and carried it south without losing momentum. Now, with the site ready and the steel soon to rise, I’m looking forward to seeing this building take shape and support Schluter Systems’ next chapter in South Carolina.