PC received the Notice to Proceed for the WSSC Bio-Energy Project Early Work Package earlier this fall. As part of this work, the team is in the process of removing hazardous materials from several buildings, installing erosion control measures, cleaning digesters and underground piping, clearing the adjacent ballfield that will house the trailer complex and beginning work on a temporary access road to the trailer complex.
December will bring demolition of the incinerator building to make room for the new bio-energy facility, demolition of ductbanks around the site and the installation of the construction trailer complex.
Work will continue through July 2020 with additional demolition, plant drain improvements and utility relocation. All this work is setting the stage for construction of the bio-energy facility, which is anticipated to begin in Spring 2020.